Progress Report - Week Commencing 16 April 2012

Progress has been significant since the last blog:
The works to the roof of Thurston House are now complete and the scaffolding has been dropped to second floor level. The majority of the brickwork repairs have been completed and this is due to be checked for any further repairs which are necessary over the next week.

Thurston House has also received its new staircase and the new windows are due to be fitted over the next couple of weeks.




Electrical and heating fittings are currently underway to the rented flats at the front of the site and the brickwork to the exterior of these is approximately 40% complete.

The houses to the rear are now fully plastered and are awaiting the new kitchen installations which are due to take place in the next month.