Progress Report - Week commencing 21 May 2012
















Most of the houses to the rear of the site have kitchens and bathrooms fitted and are undergoing final works in order that we can check the units for any faults that we need to be rectified prior to their handover to us.

The external works are now underway and the fencing and hard landscaping to the rear of the site is almost complete.






Thurston House now has its new windows installed which are uPVC sash windows to stay in keeping with the original architecture.  The walls are in the process of being dry-lined and plastered and internal decoration will be underway soon.









The flats are now fully plastered out are currently being decorated internally.  The brickwork is approximately 70% complete and all works to the roof is complete.