Thurston House

Thurston House
Thurston House Redevelopment

Thursday, 2 June 2011

Progress Report - week commencing 31 May 2011

This week has seen good progress on site.  The sign-boards have been errected and the site office and site facility units have been delivered.   This allows the demolition of the small bungalow to the rear of Thurston House to take place, this had previously been used to provide on-site facilities. 

The removal of all asbestos materials from Thurston House has been completed and most of the internal fixtures and fittings have been removed and are stacked awaiting collection for recycling (a licensed waste management company have been appointed to deal with this).

The technical approval for the Section 38 has been registered which will allow the construction of the road to take place prior to the start of construction.  This will help the contractor to minimise the amount of mud and dirt being carried out onto the main highway.

There are a number of photographs below showing how the site looks this week:

Signboards

Front of Thurston House

Site office

Rear of Lincoln Road - Items for recycling 

Rear of Thurston House

Internal Thurston House

Bathroom Thurston House