In order to ensure that the integrity of the structure of Thurston House is upheld a new concrete wall is being constructed within the basement which will become the substructure for the new rear wall.
The next few weeks will see the continued careful demolition of the rear elevation and the erection of scaffolding to Thurston House which will allow access to the roof which will be gradually removed and replaced utilising as many of the existing tiles as is possible and replacing and missing broken tiles with a similar one.