Friday, 21 October 2011

Progress Report - Week Commencing 17 Oct 2011



The foundations to the flats and 7 of the 9 houses are now up to beam level and the below ground drainage work is well underway for these units.










Rebuilding of the rear extension is now well underway with the blockwork complete and the brickwork approximately two-thirds complete.  The bricks which have been used were saved from the demolition of the extension so that they are in keeping with the rest of the building.







The adoptable road is installed up to base course and the section of road beyond Thurston House in now under construction.







Work is continuing to Thurston House roof and internals, however access is limited due to health and safety issues.  A full update will be given once access is granted.

Tuesday, 4 October 2011

Progress Report - Week Commencing 25 September 2011




Progress on-site has again been signficant.  The works to the roof are ongoing and there have been no major problems uncovered so far.  A stonemason has been employed to repair or replace and of the damaged stone as necessary.










The replacement wall to the rear elevation of Thurston House is now well underway.















The foundations and blockwork has now completed to the new build properties and work has now commenced in laying the services to these properties.