Progress Report - Week Commencing 17 Oct 2011



The foundations to the flats and 7 of the 9 houses are now up to beam level and the below ground drainage work is well underway for these units.










Rebuilding of the rear extension is now well underway with the blockwork complete and the brickwork approximately two-thirds complete.  The bricks which have been used were saved from the demolition of the extension so that they are in keeping with the rest of the building.







The adoptable road is installed up to base course and the section of road beyond Thurston House in now under construction.







Work is continuing to Thurston House roof and internals, however access is limited due to health and safety issues.  A full update will be given once access is granted.