Friday, 11 November 2011

Progress Report - Week Commencing 7 November 2011








The studding to the walls in Thurston House is now well underway and the floating floor to the ground floor is complete. The work is continuing to the retiling of the roof and the stonemason has now commenced work to repair/replace and worn or damaged stonework.














The rebuilding of the rear elevation to Thurston


House is now approximately 70% complete.















Ground floor timber frame has been erected to the flats and the scaffolding is currently being errected to be allow the second floor frames to be put in place.













Foundations are complete for 7 of the new homes to the rear of Thurston House are complete and foundations to the final two units are now well underway.