Thursday, 28 June 2012

Progress Report - Week Commencing 25 June 2012


The houses are now almost complete and the external landscaping is well underway.  Once the boilers are commissioned and the units are fully complete an inspection of the units to highlight any remaining issues which need to be dealt with prior to handover of the units.




Thurston House is now fully plastered and has had the first coat of paint.  The bathrooms are now in and the kitchens are in the process of being fitted.  It was originally hoped to keep the original door but unfortunately due to the change in the stairs layout a new door will be required and we are in the process of sourcing a suitable replacement.



The scaffold to the flats has now been dropped similarly to Thurston House these are fully plastered and the first coat of paint has been completed.  The bathrooms are in and the kitchens are in the process of being fitted.

Handover of all units is still expected early September 2012.



If you are interested in either renting (housing team) or buying a part-buy/part-rent property (marketing team) please contact our main reception on 01733 295400 and ask to speak with the relevant team.

If you have any queries regarding the development please contact me on 01733 295465.

Beverly Hill


Development Officer