The brickwork to the houses at the rear of the site has now been completed; internally the plastering is underway and the first coat of paint is being applied.
![](https://blogger.googleusercontent.com/img/b/R29vZ2xl/AVvXsEglmqxypJOngidtO_cdq5e2WOMVZd2yNpwivAMgaIH0GHWQg2BaBLGfbtzsUDNjkQmU18tLHgsEpjTyTbMcSnQ9PYn3wlkve8Yn4ibxPApKH_dFpMc29kSpq30jLbznZuT7RQrynHz_Dn8/s320/2011-03-02-Lincoln+Road+052.jpg)
The PV installation to all the houses is also now complete
There has not been much progress to the apartments in Thurston House recenlty as there were some changes needed to the wiring layout to ensure that the kitchen and room layouts best met the needs of the new residents. As this is now all agreed work will recommence to complete the wiring before plastering is commenced.
![](https://blogger.googleusercontent.com/img/b/R29vZ2xl/AVvXsEjuVooN2eCrqsumjvvPUlXrQfMIDFwYF8rPeYi7W-d3s-2WRIoJi5v7Ur-Ip0IeMb5P-3pO4u47dQQ3C-GvMZ_5W2ZOs7-9sUm2u2eSnlYW7PXX_8VoN3JIog7qBjuxpeJWY4qjl1d4rxw/s320/2011-03-02-Lincoln+Road+031.jpg)
External brickwork has now been commenced to the block of flats at the front of the site and internally the electrical installation is now well underway.
You may also notice that there is currently roadworks on Lincoln Road itself and this is the final part of the utility connections needed for the site. These were delayed in order that the disruption on Lincoln Road was kept to a minimum.
The contractor is forecasting that the work is still slightly ahead of programme and that the homes will be ready for the September 2012 programmed completion date.
If you have any queries regarding these new homes please do not hesitate to contact me on 01733 295465.