Monday, 13 February 2012

Progress Report - Week Commencing 13 February 2012

The winter weather has finally arrived, however as the new houses to the rear of the site are fully roofed and the pv panels fitted, this is not causing us major difficulties. The cold weather will delay the brick laying, however work can continue on the interiors and the electric and plumbing work to the houses is complete. The boarding out is almost complete with plastering to commence shortly.

With regard to the newbuild flats to the front of the site - these were slightly delayed due to the change in planning application to in-roof pv panels. This change has now been approved and work is progressing with the installation of the electrics and plumbing to these flats.



The refubishment of Thurston House is continuing, the replacement work to the roof and the repair work to the chimneys is almost complete. The rebuilding of the rear gable wall is now fully completed and work to repair any other exterior brickwork as necessary is underway. Installation is continuing to the interior with electrics and plumbing complete the to the ground floor apartments. We are expecting the window installation to commence shortly.

If you have any questions regarding the work taking place please contact me on 01733 295465.

Beverly Hill
Development Officer