Thursday, 19 January 2012

Progress Report - Week Commencing 16 January 2012

After a quiet time over the Christmas period work work on site is progressing quickly and is ahead of programme. The first electrical and plumbing installation to Thurston House is well underway and the boarding out will commence once this work is complete. The last of the chimney's has been taken down and will be rebuilt shortly.



The houses to the rear of the site are all at roof level and will now be roofed out and the brickwork started. The electrical and plumbing installations will now begin and the windows are due on site shortly.






The newbuild block of flats to the front of the site are currently at roof level and the roof has been loaded ready for tiling.










We have now received full approval to the non-material planning amendments which includes the use of in-roof PV panels to the flat roofs and on-roof PV panels to the house roofs at the rear of the site. The us of PV panels is needed in order to comply with the high level of sustainability required for the new homes.



If you would like any further information regarding this site please contact me on 01733 295465



Beverly Hill

Project Officer