The weather has been kind so far and this has meant that the contractor has been able to install the roof trusses to both the block of flats at the front of the site and two of the houses to the rear. The installation to the remaining roof trusses will be installed over the next few weeks as long as we don't get any adverse weather.
Having the roofs in place means that the properties can be made weather tight and as such work reduces the risk of construction delays due to adverse weather.
The rear gable wall to Thurston House is now almost fully completed and the work to the roof is continuing.
Internally first fix has commenced with the plumbing pipework and electrics work underway.