Tuesday, 2 October 2012

Completion - 7 September 2012

The new homes at Lincoln Road were handed over to Accent Nene on 7 September 2012 from  Larkfleet.  The new residents moved into the rented properties over the weekend and the first shared owner moved in of 27 September 2012.   There are a few photographs below which I hope you agree show that the development was a success and that Thurston House sits well in its new surroundings.




Thursday, 28 June 2012

Progress Report - Week Commencing 25 June 2012


The houses are now almost complete and the external landscaping is well underway.  Once the boilers are commissioned and the units are fully complete an inspection of the units to highlight any remaining issues which need to be dealt with prior to handover of the units.




Thurston House is now fully plastered and has had the first coat of paint.  The bathrooms are now in and the kitchens are in the process of being fitted.  It was originally hoped to keep the original door but unfortunately due to the change in the stairs layout a new door will be required and we are in the process of sourcing a suitable replacement.



The scaffold to the flats has now been dropped similarly to Thurston House these are fully plastered and the first coat of paint has been completed.  The bathrooms are in and the kitchens are in the process of being fitted.

Handover of all units is still expected early September 2012.



If you are interested in either renting (housing team) or buying a part-buy/part-rent property (marketing team) please contact our main reception on 01733 295400 and ask to speak with the relevant team.

If you have any queries regarding the development please contact me on 01733 295465.

Beverly Hill


Development Officer

Friday, 25 May 2012

Progress Report - Week commencing 21 May 2012
















Most of the houses to the rear of the site have kitchens and bathrooms fitted and are undergoing final works in order that we can check the units for any faults that we need to be rectified prior to their handover to us.

The external works are now underway and the fencing and hard landscaping to the rear of the site is almost complete.






Thurston House now has its new windows installed which are uPVC sash windows to stay in keeping with the original architecture.  The walls are in the process of being dry-lined and plastered and internal decoration will be underway soon.









The flats are now fully plastered out are currently being decorated internally.  The brickwork is approximately 70% complete and all works to the roof is complete.



Tuesday, 17 April 2012

Progress Report - Week Commencing 16 April 2012

Progress has been significant since the last blog:
The works to the roof of Thurston House are now complete and the scaffolding has been dropped to second floor level. The majority of the brickwork repairs have been completed and this is due to be checked for any further repairs which are necessary over the next week.

Thurston House has also received its new staircase and the new windows are due to be fitted over the next couple of weeks.




Electrical and heating fittings are currently underway to the rented flats at the front of the site and the brickwork to the exterior of these is approximately 40% complete.

The houses to the rear are now fully plastered and are awaiting the new kitchen installations which are due to take place in the next month.

If you would like any further information regarding the site please contact me on 01733 295465,

Beverly Hill
Development Officer




Monday, 5 March 2012

Progress Report - week commencing 5 March 2012



The brickwork to the houses at the rear of the site has now been completed; internally the plastering is underway and the first coat of paint is being applied.





The PV installation to all the houses is also now complete




There has not been much progress to the apartments in Thurston House recenlty as there were some changes needed to the wiring layout to ensure that the kitchen and room layouts best met the needs of the new residents. As this is now all agreed work will recommence to complete the wiring before plastering is commenced.




External brickwork has now been commenced to the block of flats at the front of the site and internally the electrical installation is now well underway.





You may also notice that there is currently roadworks on Lincoln Road itself and this is the final part of the utility connections needed for the site. These were delayed in order that the disruption on Lincoln Road was kept to a minimum.

The contractor is forecasting that the work is still slightly ahead of programme and that the homes will be ready for the September 2012 programmed completion date.

If you have any queries regarding these new homes please do not hesitate to contact me on 01733 295465.

Monday, 13 February 2012

Progress Report - Week Commencing 13 February 2012

The winter weather has finally arrived, however as the new houses to the rear of the site are fully roofed and the pv panels fitted, this is not causing us major difficulties. The cold weather will delay the brick laying, however work can continue on the interiors and the electric and plumbing work to the houses is complete. The boarding out is almost complete with plastering to commence shortly.

With regard to the newbuild flats to the front of the site - these were slightly delayed due to the change in planning application to in-roof pv panels. This change has now been approved and work is progressing with the installation of the electrics and plumbing to these flats.



The refubishment of Thurston House is continuing, the replacement work to the roof and the repair work to the chimneys is almost complete. The rebuilding of the rear gable wall is now fully completed and work to repair any other exterior brickwork as necessary is underway. Installation is continuing to the interior with electrics and plumbing complete the to the ground floor apartments. We are expecting the window installation to commence shortly.

If you have any questions regarding the work taking place please contact me on 01733 295465.

Beverly Hill
Development Officer
Accent Nene Limited

Thursday, 19 January 2012

Progress Report - Week Commencing 16 January 2012

After a quiet time over the Christmas period work work on site is progressing quickly and is ahead of programme. The first electrical and plumbing installation to Thurston House is well underway and the boarding out will commence once this work is complete. The last of the chimney's has been taken down and will be rebuilt shortly.



The houses to the rear of the site are all at roof level and will now be roofed out and the brickwork started. The electrical and plumbing installations will now begin and the windows are due on site shortly.






The newbuild block of flats to the front of the site are currently at roof level and the roof has been loaded ready for tiling.










We have now received full approval to the non-material planning amendments which includes the use of in-roof PV panels to the flat roofs and on-roof PV panels to the house roofs at the rear of the site. The us of PV panels is needed in order to comply with the high level of sustainability required for the new homes.



If you would like any further information regarding this site please contact me on 01733 295465



Beverly Hill

Project Officer